Project Approval

  • APPROVAL OF PRELIMINARY DESIGN Duration: 2(two) month
    Project approval by the Board of Directors of LIVIZA GROUP
  • Validation in plenary session by the LIVIZA General Assembly
  • approval and validation of the principle of the draft Presentation by LIVIZA at the AU of the project financing principle
  • Individual presentation to each country for approval of the preliminary project route in their territory and connection route with the neighboring countries

COUNTRY BY COUNTRY VALIDATION OF THE PROJECT FINANCING PRINCIPLE : Duration:6(six) month

  • Deployment of LIVIZA GROUP teams in each country for the individual presentation of the project financing principle in their country
  • Obtening an agreement
  • Agreements signature between the Goverment and LIVIZA GROUP
  • REDEFINING OF THE PROJECT ROUTE BY THE EXPERTS OF EACH COUNTRY AND LIVIZA EXPERTS
    Deployment in each country of the LIVIZA technical expert
  • Redefining project route with the collaboration of the experts of the local government and the A.U. representative
  • Validation of the project route design

PHASING FOR STUDIES, DESIGN AND START OF WORK BY COUNTRY

STUDIES AND DESIGN – PHASE 1 36000 (Thirty six thousand) km cumulative duration: 8 (eight) years

  • Procurement contract for a complete environment analysis that will consider also the phase 2 of the project
  • Procurement contrat for the engineering consulting companies(topography, geotechnical, plot, plans, technica l prescriptions, etc.)
  • Validation of the studies and design by LIVIZA GROUP in collaboration with the government experts .
  • Approval of the studies and design
  • Launch the tenders for the constructions companies

CONSTRUCTION -PHASE 1 36000 (thirty six thousand) km cumulative duration: 12 (twelve) years

  • Progressive award of work to the construction companies
  • Signing of the procurement contract with the construction companies
  • Launching of tenders consulting compagnies for the supervision and control
  • Award of contract and signature of procurement contract Start of work

STUDIES AND DESIGN – PHASE 2 40000 (forty thousand) km cumulative duration: 8 (eight) years

  • Procurement contrat for the engineering consulting technical prescriptions, etc.)
  • Validation of the studies and design by LIVIZA GROUP in collaboration with the government experts
  • Approval of the studies and design
  • Launch the tenders for the constructions companies

CONSTRUCTION- PHASE 2 40000 (forty thousand ) kilometers cumulative duration:15(fifteen)years

  • Progressive award of work to the construction companies in scope of 100(hundred) kilometers maximum to reduce
    Signing of the procurement contract with the construction companies
  • Launching of tenders consulting companies for the supervision and control
  • Award of contract and signature of procurement contract Start of work

CONSTRUCTION OF AN UNDERWATER TUNNEL TO ACCESS MADAGASCAR BY HIGHWAY AND RAILWAY cumulative duration:12(twelve) years

  • Award and procurement contract with the specialized ingineering companies
  • Validation and approval of the studies and design
  • Launch the tenders for specialized constructions companies Procurement contrat with the construction companies
    Selection of the control and supervision consulting companies and procurement contract
  • Start of work